Concept development and operational implementation of a process for checking and, if necessary, reconfiguring around 30,000 residue containers at the Philippsburg NPP site

Details
Customer
EnBW Kernkraft GmbH
Country
Germany
Location
Philippsburg
Duration
2023 – 2024
Topics

Concept development and operational implementation of a process for checking and, if necessary, reconfiguring around 30,000 residue containers at the Philippsburg NPP site

Our services at a glance:

  • Reviewing the instructions and identifying the necessary measures
  • Reviewing the conditions on site and creating a list of the delta between the requirements and the actual conditions
  • Describing the processes required to close the delta between the requirements and the actual conditions
  • Planning and describing the processes in a level of detail appropriate for operational implementation
  • Determining the throughput and capacity utilisation of the individual process steps for the processing of around 30,000 containers
  • Determining scenarios for various target variables and their influence on the process design. The scenarios include
    – Shortest possible duration for carrying out the process for all containers
    – most economical scenario
    – most flexible scenario to take into account new findings on the required processing
  • Design and implementation of training courses for operational staff on processing and documenting residue